Texas Governor Orders Halt To New Data Centers Weeks After Issuing Moratorium
One month after Texas Governor Greg Abbott ordered a pause on Texas data center approvals pending an audit, overnight the governor doubled down and ordered the state’s environmental watchdog to withhold permits for new data centers until an audit of risks to the power grid is complete.
No authorizations can be given until the Electric Reliability Council of Texas, or Ercot, completes its review, Abbott said in a statement on Monday.
Gov. Abbott directed the TCEQ to halt any new permits authorizing data center projects until ERCOT completes its audit.
— Governor Abbott Press Office (@GovAbbottPress) September 21, 2026
No state agency shall move forward with approvals related to the development of data centers until that information is acquired. pic.twitter.com/MG2s0EKf8x
This matters a lot for the US data center rollout because as the chart from Apollo below shows, Texas is home of one-fifth of the US’s data center pipeline in terms of IT power capacity, by far the largest of any single state.
In his statement, Abbott said that data center projects must prove they can cover all electrical infrastructure costs, use no water needed by local communities, and result in lower bills for households. The governor also said he would work with state legislators to eliminate any financial incentives for the hubs.
The governor is doubling down on an effective moratorium on new AI hubs amid concern that the vast sites are compromising the state grid and water resources. The proliferation of data centers is set to be a key issue in midterm elections in November, with President Donald Trump’s enthusiasm for expansion coming up against mounting public concern, mostly due to soaring power bills.
The permitting halt comes amid growing opposition to data centers across the US. Some 45 projects, worth $68 billion, were blocked or delayed by local pushback between April and June, according to research group Data Center Watch. Trump, meanwhile, has sought to drive the industry forward, warning that a slowdown could offer China an advantage in the AI race.
Texas, the biggest US energy powerhouse, has until now been at the forefront of the AI boom, but it has also struggled to connect data centers to the grid. As we reported at the time, Abbott last month ordered Ercot, along with the Public Utility Commission of Texas, to audit all data centers in the grid queue before issuing further approvals. Regulators subsequently set a mid-December deadline for project reviews.